| 1 |
GETCO
|
CE (Projects)/II/T- 3/2351/400KVA-V P3/2319&2320
|
"400KV D/C Amreli-Vadinar
Line Twin ACSR Moose conductor"
|
61.572
|
05.03.2018
|
Stringing completed 52.08 KM out of 61
|
| 2 |
GETCO
|
"CE(Projects)/II/T-2/E- 2507/220KV S-G/840 and
841 Dtd 31.12.2021"
|
Supply, Erection, Testing & Commissioning of 220kV D/C Shapar - Ghiyavad Line on D/C Tower with AL-59 Conductor with OPGW Cable - 42.360 kM on turnkey basis under Kishan Suryoday Yojana.
|
42.360
|
31.12.2021
|
"Under
progress"
|
| 3 |
GETCO
|
"CE(Projects)/II/T-3/E-
2512/220KV LILO
vallabhipur/8412 and Dtd 28.09.2021
"
|
Supply, Erection, Testing & Commissioning of LILO of one circuit of 220kV D/C BECL – Botad line at 220kV Vallabhipur S/S on D/C Tower with ACSR Zebra Conductor with OPGW cable having route length of 5.401 kM.
|
5.401
|
28.09.2021
|
"Under
progress"
|
| 4 |
GETCO
|
CE(Projects)/II/T-3/E-2485/220KV S- G/85 and Dtd 2.01.2021
|
Balance work of Supply & Erection of 220kV D/C Gavasad - Salejada line on tower with AL-59 Conductor (Equivalent weight of ACSR Zebra Conductor) - 96.27 km on turnkey basis. (Conductor supplied by GETCO).
|
96.270
|
02.01.2021
|
Stringing completed 56 KM out of 96 KM
|
| 5 |
GETCO
|
CE(Projects)/II/T-3/2475/220KV B- C/4674 and Dtd 27.11.2020
|
Balance work of Supply & Erection of 220kV D/C Botad - Chorania line on tower with AL-59 Conductor (Equivalent weight of ACSR Zebra Conductor) - 51.62 km on turnkey basis. (Conductor supplied by GETCO).
|
51.620
|
27.11.2020
|
Completed stringing 26 KM out of 51 KM
|
|
|
|
Total
|
257.223
|
|
|